Client: Turner Construction
Duration: 2 Years
Scope: 126,000 sq ft of hot waterproofing.
Owner: Hamilton County

View All Projects

Description of Work

Removed existing waterproofing, concrete repairs, installed new waterproofing, Remove and replaced expansion joints, sealants.

Accomplishments

Removing existing waterproofing (multiple different waterproofing), Even hazardous 100 year old tar / Largest waterproofing project in Cincinnati and Finished right on time.